Rural road construction far behind target in April-Sept: NSO data






At a time when the government is pushing for higher capex, the length of rural roads constructed under the Pradhan Mantri Gram Sadak Yojana (PMGSY) has again fallen short of its target.


For instance, only 41 per cent of the target for April-September of FY23 could be completed during the stipulated period.


According to data released by the National Statistical Office (NSO) of its latest Twenty Point Programme (TPP) progress report, only 9,753 km of roads could be constructed in the first six months of FY23.


The TPP report monitors over 50 different schemes and plans on a quarterly basis. The rural development scheme has been a laggard in the recent past, as it has been missing its targets for the April-September period since FY17.


Performance of a programme is considered “poor” by the NSO if the level of targets achieved is below 80 per cent.


During April-September 2016, the scheme achieved 96 per cent of its target, followed by completion of only 52 per cent of the works in the following year. During FY13 to FY15, the programme achieved above 100 per cent target for the first half.


The worst performance of the scheme was during the first half of FY19 when only 3,379 km of roads (13 per cent) were constructed against a target of 26,246 km.


Currently in its third phase, PMGSY was launched as a centrally-sponsored scheme in 2000.


It was to provide all-weather road connectivity to unconnected areas in the country as part of a poverty-reduction strategy.


During the Budget for 2022-23, the Centre raised allocation to the programme by nearly 36 per cent to Rs 19,000 crore from Rs 15,000 crore in the previous year. This comes even as the programme’s spending has been below the budgeted amount in recent years.


According to a written reply filed by Union minister of state for rural development Sadhvi Niranjan Jyoti in the Lok Sabha last year, nearly 700,000 km of road (around 99 per cent of the sanctioned length) had been completed under the first and second phases of the scheme.


However, only 45,945 km of the targeted 125,000 km has been constructed in the third phase.


This phase focuses on consolidation of the rural road network to and from Gramin agricultural markets, higher secondary schools and hospitals.


The ministry of statistics and programme implementation (MoSPI) is tasked with monitoring 65 items under the TTP.


Of these, 17 are reported on a quarterly basis, and the others on an annual basis.


Besides construction of rural roads, the provision of revolving funds (61 per cent) and Community Investment Fund (44 per cent) to self-help groups (SHGs) also performed poorly during April-September.

















Progress report for PMGSY (in KM)


Year

Target

Achieved

%completion

April-Sep 2013

8854

9393

106

April-Sep 2014

8854

16,716

189

April- Sep 2015

7800

14,574

187

April-Sep 2016

24,402

23,474

96

April- Sep 2017

28,492

14,859

52

April-Sep 2018

29,000

8200

28

April- Sep 2019

26,246

3379

13

April- Sep 2020

23,084

4158

18

April-Sep 2021

30,854

6248

20

April-Sep 2022

23,590

9753

41


For more latest Economy News Click Here 

Read original article here

Denial of responsibility! FineRadar is an automatic aggregator around the global media. All the content are available free on Internet. We have just arranged it in one platform for educational purpose only. In each content, the hyperlink to the primary source is specified. All trademarks belong to their rightful owners, all materials to their authors. If you are the owner of the content and do not want us to publish your materials on our website, please contact us by email – abuse@fineradar.com. The content will be deleted within 24 hours.
AprilSeptCapexconstructiondataEconomyEconomy NewsFine RadarHeadlinesIndian EconomymospiNSOPMGSY roadsPMGSY Rural Roads ProjectPradhan Mantri Gram SadakRoadroad constructionRuralTargetThe ministry of statistics & programme implementationTwenty Point ProgrammeUnion Minister of State for Rural Development Sadhvi Niranjan JyotiWorld economy News
Comments (0)
Add Comment